Tens of thousands of public sector workers in Sri Lanka protest austerity budget - World Socialist Web Site Geopolitical Factors Shaping Sri Lanka’s Critical Minerals Prospects – Analysis - Eurasia Review Launch Preview: Russian, Chinese, and SpaceX rockets to launch space station missions First Pakistani Astronaut Enroute to Tiangong Sri Lanka's CCF lands $6M Incofin facility for women borrowers - Dealroom White House Requests Billions for NASA, Golden Dome in Next CR NASA+ Content Coming to Big Screen at Greenbelt, Maryland Cinema Sri Lanka win ICC Women's Emerging Nations Trophy 2026 - ICC Sri Lanka A vs India A at Doha, DP World Men's Asia Cup Rising Stars, Semi-Final, 26 Nov 2026 - BCCI APOD: 2026 November 25 – SPHEREx Seeing Through Dust
SRI LANKA NEWS

Subpar coal : Supplier wasn’t even registered at the time Tender was called - Sri Lanka Mirror

Lanka Hit News • Apr 7, 2026 · 7mo ago • 3 min read
Share:

A special audit report on coal procurement for the 2025/2026 season has revealed that, as at the date on which advertisements were published calling for bids by the Lanka Coal Company for the purchase of coal for the Lakvijaya Power Plant, the Trident Company, which was ultimately awarded the tender, had not yet completed its registration.

The Auditor General has further disclosed in this special audit report that, in supplying coal to Sri Lanka, the laboratory whose reports were obtained at the port of loading by the controversial Trident Company had had its licence revoked.

The Auditor General issued this report following a recent communication made by the Committee on Public Enterprises (COPE) to the National Audit Office.

COPE had requested a report from the Auditor General regarding both the procurement process and the failure of the coal purchased for the Norochcholai Lakvijaya Power Plant for the 2025/2026 season to meet the expected standards.

Accordingly, the National Audit Office has now released a special audit report on the coal procurement process carried out by the Lanka Coal Company for the Lakvijaya Power Plant, as well as on coal procurement for the 2025/2026 season.

The report states that the procurement notice had clearly specified that bids would be called only from suppliers who had completed their registration by the date of publication of the advertisement.

However, bids had also been invited from three suppliers who had not confirmed their registration by paying the full registration fee by that date, and the Trident Company selected for this procurement had likewise not confirmed its registration at that time, the Auditor General has observed.

The coal purchased is subjected to testing by an independent inspector at both the port of loading and the port of discharge to verify whether it meets the standards required for the Lakvijaya Power Plant. However, as the seller-appointed Mitra SK South Africa did not possess accreditation to test coal samples against the required standards, the testing was assigned to an Indonesian company, PT Mitra SK Analisa Testama Samarinda, whose licence had been cancelled by 29 December 2025, to issue the relevant reports.

Furthermore, the audit did not find evidence that the licence of the said company had been renewed as at 31 March 2026.

Nevertheless, the audit report indicates that the port-of-loading reports relating to all 12 shipments received had been issued by Mitra SK South Africa, which lacked proper accreditation.

The report further notes that, despite discrepancies between the port-of-loading test reports and the data obtained from the main control unit of the Lakvijaya Power Plant, and despite the availability of several alternative options for verification, the Lanka Coal Company had failed to utilise any of those options to confirm the accuracy of the loading port reports.

It is also pointed out that, although coal cannot be unloaded in Sri Lanka throughout the year and therefore imports must be maximised during the available window, the Lanka Coal Company had failed to carry out procurement in a manner that would allow any shipments to be received during the 40-day period from 13 November to 30 December 2025.

Subsequently, due to the arrival of fewer vessels than required, coal had to be procured through an emergency procurement on 18 March this year. The Auditor General has revealed that the selected company, Taranjot Resources (Private) Limited, had, within the 36 months prior to obtaining its registration, failed to supply coal meeting or exceeding the rejected threshold gross calorific value of 5,900 kilocalories required by the Lakvijaya Power Plant.

In light of these circumstances, the Auditor General has further warned in the report that the inability to ensure the timely arrival of coal shipments, coupled with potential uncontrollable future conditions, could adversely affect the continuous supply of electricity if sufficient coal is not secured to meet the requirements of the Lakvijaya Power Plant.